Almost all renovation projects will inevitably face delay. At the end of the day, we accept this fact and the question turns to "for how long" will this delay be?
It is now 2 weeks since Mr Contractor promised the 3 week deadline; which leaves us with only one week to go for works to be completed. We were skeptics at the 3 week deadline, not because it isn't possible (anything is possible) but more so that this isn't a big enough job for Mr Contractor to pour in all his resources.
With a slight hiccup with tile supplies from MML last week (MML was scheduled only to deliver in September - which was really not acceptable so Mr and Mrs Kong kicked up a huge fuss), that will probably be Mr Contractor's most convenient excuse.
On the bright side, the tilers did work today. Mr Contractor was bright and early. Mr Carpenter has started to take our kitchen cabinets a little more seriously after we told him that we are moving in on the 30th of August, and we should have all our kitchen white goods ordered by the end of the week!
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment